Green Contracting has performed ongoing maintenance and construction operations at Johns Hopkins Hospital for the past 20 years. In November 1997, the Hospital was faced with a significant shortage in its chilled water capacity with the opening of two new buildings. Design of the Chiller Plant upgrade and Utility Tunnel projects was only 50% complete. Based on our ongoing relationship with the Hospital, we were charged with completing this fast track multifaceted project. We established a Design Team to oversee the design and selection of equipment and a Construction Team to oversee the planning and implementation of construction. Substantial completion of the Chiller Plant upgrade met the owner's deadline and additional phases are progressing on schedule. | |||||||
![]() |
|||||||
![]() |
|
||||||